One down, two more to go.

Traffic disruptions will continue at Cochrane at-level railway crossings for the balance of the week as the town and Canadian Pacific Railway crews continue maintenance work. 

The Centre Ave. crossing is scheduled to be closed Wednesday, May 4 and Thursday, May 5.

That will be followed by the closure of the River Ave. crossing from May 6 to 7.

Officials have warned that May 8 to 10 have been set aside as extra days of work should there be any postponements or delays.

On May 3, town and CPR crews completed work on the 5th Ave. railway crossing on schedule.